Project Update - Fairwater Community Campus

Writer's picture: CMB EngineeringCMB Engineering

The BESL team has made excellent progress on the Fairwater Community Campus project over the past 12 weeks. Having built momentum since stepping in as interim Principal Contractor in November, both the project team and supply chain are fully mobilised and driving forward at a good pace.

 

The Health & Wellbeing Block (HWB) is now watertight, with internal fit-out progressing smoothly. The screed has been laid, second-fix M&E services are now underway and externally, the first of the 5-a-side All-Weather pitches has been completed.

 

Cantonian High School is following a similar trajectory, with internal fit-out advancing well and the first screed areas to be finished shortly. The external envelope progress is particularly impressive, with work ongoing across all elevations, including SFS, cladding, and brickwork. For the Riverbank and Woodlands areas, the structural floor slabs have been completed, which now allows work to begin on fire protection and the building envelope. Meanwhile, installation of photovoltaic panels and other roof finishes is progressing steadily also.

 

Credit goes to the BESL team and entire supply chain who have helped make this progress possible. We look forward to providing another update on this exciting development soon.



















CMB COLOUR.png
bottom of page
Consent Preferences